Traffic Calming Update (August 2024) – When will the NWRR open?

The Parish Clerk received an email from WNC’s Major Projects Manager stating:- WNC’s contractor Balfour Beatty will complete the construction of the Northampton North West Relief Road (NNWRR) by September […]

Traffic Calming Update (July 2024)

The WNC project manager confirmed there is no further update from June 2024 as they are waiting for their consultant, WSP, to complete their latest assessment of the traffic model. […]

Traffic Calming Update (June 2024)

WNC have provided an update to the questions proposed in May 2024. Q1. Please can you clarify what would happen if planning conditions were not met by WNC or the […]

Traffic Calming Update (May 2024)

For an overview please see:- https://boughtonparishcouncil.co.uk/traffic-calming/traffic-calming-february-2024 For the last update please see:- https://boughtonparishcouncil.co.uk/traffic-calming/traffic-calming-update-march-2024 WNC’s project manager for the NWRR has recently changed. This has inevitably caused some delay in receiving updates. The […]

Traffic Calming Update (March 2024)

The Parish Clerk asked the project manager of the NWRR the following questions:- Q1. How long do Ward Councillors have to provide feedback to you? The work WCN have been […]

History of the Traffic Calming proposals (February 2024)

As the hyperlinks do not work in the PDF, they are copied below. https://www.westnorthants.gov.uk/current-minerals-and-waste-planning-applications/north-west-relief-road https://www.westnorthants.gov.uk/current-minerals-and-waste-planning-applications/north-west-relief-road